So 14 days to, topping was the same on 3 October, Mr. Kriesel has kept a really great judge's decision. Then the new home was poured properly, have extra real good Polish vodka worried. In the next few days there was really bustle in the house, 5 craftsmen, two plumbers and two electricians on the potter sometimes until midnight. The guys do really good work.
Made
was until now.
- covered roof
- facade transitions dressed and ground built
- dormer from the porch and bathroom and covered
- used bathroom window (fits only unfortunately, the window is a bit too small. But it will still be exchanged)
- wastewater - and laid water pipes, electrical equipment installed
- was isolated floors and underfloor heating designed towel connected
- water meter installed
- screed introduced
- walls are mostly covered and vorgespachtelt
| view from the front of the porch |
| rear view of the bay window and the bathroom, pictures are from 02.10.2009 |
| over again with roof tiles and partly covered |
| also from behind a few days after the ceremony. |
| water lines are down the hall to the kitchen and heating to the heater in the porch |
| there in the "Garden "is the excavator for the hole in the ground where the absorber mats come inside for the heat pump |
| The heat pump and the absorber mats |
| heating pipes in the living room |
| heating pipes and distribution at the top |
| and screed on it |