building costs
The building costs incurred to date to 03 December I've put together.
brokerage costs: 2500 €
Official Map: 1344.70 €
creating a negative certificate: 62,10 €
Notary fees: 385.98 €
house number allocation: 15.55 €
excerpts from the real estate figures: 200 €
examination of the contract: 260 €
estate transfer tax: 700 €
soil report: 875 €
planning application: € 612.50 +
loaders Fuel: 240 €
drinking water house connection: 1071 €
Electricity: € 1029.41
Bauwasserschacht with 3 months rent: € 455.64
KG-pipes (sewage): 200 €
Conduit: 178,50 €
drainage material: 100 €
Baustromanschluß: 327.15 €
Gebäudeeinmessung: 695.40 €
coarse and marking out: € 523.60 +
earthworks construction road including compression testing: 2812.78 €
construction sites: 333.20 €
structural engineer: 916 €
request to remove two fruit trees including scrub 6 square meter: 52 €
excerpts from real estate map: 15 €
negative testimony (State Environmental Agency): 20 €
priority notice, registrar of copy: 366 €
acceptance of the chimney by Schorsteinfeger: 52.73 €
Construction supervisor: 1071 €
---------------------------------------------
---------- Total: 17415.24 €