Monday, December 3, 2007

Farm Lessons 14 Image

plastering

From 16.11. -21.11. 2007, the interior cleaners were employed. The result is quite spectacular.



Causes Of Particles In Urine

What ever so happened

Sorry I have to blog less and less time and energy. Therefore, the posts are so klecker as.
I once made a small list of the trades that have already been completed.

28.09. 2007 Date of Electricians
03.11. 2007 Tile Specialists
08.11. 2007 electrical installation
13.11. 2007 windows and doors
16.11. -21.11. 2007 Internal plaster
17.11. 2007 Meeting with tile
19.11. 2007 Sims box
20.11. 2007 Dismantling of arms
21.11. 2007 deep drilling
21.11. 2007 Plumbing, heating
26.11. 2007 drinking water connection to the house
26.11. 2007 floor
27.11. 2007 electrical wiring, electrical item 2
28.11. 2007 screed
01.12. 2007 rain drainage, waste water into individual performance

Every Day Ms Symptoms

building costs

The building costs incurred to date to 03 December I've put together.

brokerage costs: 2500 €
Official Map: 1344.70 €
creating a negative certificate: 62,10 €
Notary fees: 385.98 €
house number allocation: 15.55 €
excerpts from the real estate figures: 200 €
examination of the contract: 260 €
estate transfer tax: 700 €
soil report: 875 €
planning application: € 612.50 +
loaders Fuel: 240 €
drinking water house connection: 1071 €
Electricity: € 1029.41
Bauwasserschacht with 3 months rent: € 455.64
KG-pipes (sewage): 200 €
Conduit: 178,50 €
drainage material: 100 €
Baustromanschluß: 327.15 €
Gebäudeeinmessung: 695.40 €
coarse and marking out: € 523.60 +
earthworks construction road including compression testing: 2812.78 €
construction sites: 333.20 €
structural engineer: 916 €
request to remove two fruit trees including scrub 6 square meter: 52 €
excerpts from real estate map: 15 €
negative testimony (State Environmental Agency): 20 €
priority notice, registrar of copy: 366 €
acceptance of the chimney by Schorsteinfeger: 52.73 €
Construction supervisor: 1071 €
---------------------------------------------
---------- Total: 17415.24 €

Sayings For Your Business

construction costs

Here I once current construction costs of 03 December 2007 brought together:

basic costs: Fries House (house, chimney, brick facing, heat pump with depth probes, floor): 126 400 €

costs: Magnetic contact switch for the kitchen window: 150 €
change of reinforcement: 145 €
extension of the ice wall: 350 €
reinforced concrete door lintel 81 €
2xWanddurchführung for fireplace: 80 €
Bewehrungsset for chimney: 240 €
interior window bars: 590 €
1 Terrace item (additional costs to window): 230 €
Catwalk and still rocks for chimney sweeps: 645 €


Registered services: handle sets of internal doors: 80 €

costs later:
tilers: Installation 3454.85 €
: 1700 , 39 €
----------------------------------------------
------------- Total: € 133,986.24